A steel mill has 7 safety inspections a month to find 163 safety hazards!

80T

1. The warning signs on the ladder of the bulk material warehouse are dirty, and the site is rectified.

2, bulk material warehouse 1 # belt head at the protection gap

3, bulk material warehouse 1# belt conveyor east side channel ground debris, on-site rectification

4, the fan room second floor 3# fan front soft connection bolts are not installed

5, the slag room weld steel package oxygen point valve box pressure surface is dirty, can not see the pressure

6, online 18# steel bag wall has slag, on-site rectification

7, the billet turning machine at the mouth of the ladder to prevent materials, site rectification

8, 2# furnace main control indoor air breathing apparatus has accumulated dust, on-site rectification

Check other stations for normal air breathing apparatus

Check the liquefied gas station**, ** liquefied gas ignition emergency measures are qualified

Spot check aid **, ** wearing air breathing apparatus qualified

120 tons:

1. There is water in the middle of the converter 8.8 meters 1#2# furnace, which has been rectified

2, 2# West side of the furnace repair box has debris, has been rectified

3, ladle repairing electric hoist limit failure, has been rectified

4. There is oil on the ground between power generation turbines, and the site is rectified.

5. The line of the distribution box near the mud filter of the filter press is bare, and the site is rectified.

6. There is a bottle of fire extinguishing gas expired in the power distribution room of the cyclone well, and the site is rectified.

7, the transition 2 #50 cart fire extinguisher expired, on-site rectification

8.2# Machine platform northeast corner power distribution cabinet leakage protector is broken, has been replaced

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop on September 5, 2017, it was found that your unit had the following problems and needs to be rectified.

1. Bulk material warehouse 1# belt head has large protection clearance

2, the second floor of the fan room 3# fan machine front soft connection bolts are not installed

     Your unit must rectify the above issues as required by September 11, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 5, 2017, it is found that your unit has the following problems and needs to be rectified.

1. The pressure surface in the oxygen point valve box of the slag room is not dirty, and the pressure is not clear.

Your unit must rectify the above issues as required by September 11, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Coding: YGJL6026

Time: 2017-9-7

Main part or content of the inspection: hazardous chemicals

80 tons:

1. The fan room No. 3 fan is fixed to the front of the butterfly valve telescopic section of the pipeline, and is separated from the fixed suspension.

2, 3 #, 4 # fan discharge tube has no signage.

3, 1#, 2# fan chimney dehydrator valve screw without rubber holster.

4, the external network gas supply 10# dehydrator fill valve is not open.

5, the external network gas supply 11 # water valve screw without rubber holster.

6. The oxygen belt tube used in the oxygen-saving day inspection shed is seriously deteriorated and the site is scrapped.

7. The south outer liquefied gas point valve box door of the east turn room is dropped.

8. The power line of the high-pressure air liquefied gas pipe and the tire vibration motor in the east turn room is chaotic.

9, 3 # casting machine 5# baking machine at the joint of the torch and hose is damaged.

10, 2# Converter east side oxygen point valve box door stack of debris and torch belt There is no fire extinguisher at the station.

120 tons:

1. Even chopsticks and other debris are placed in the oxygen valve box on the west side of the zero-meter two cold room of the billet casting machine.

2. Auxiliary 21st off-line medium-packed roasting machine butterfly valve upper purge point using single valve

3. There is no anti-static jumper wire on the flange of the new baking pan butterfly valve on the east side of the auxiliary two-day cabin.

4, the external network 5 # recycling dehydrator hydrating small

5, the external network 5 # gas dehydrator dangerous source warning sign dirty, can not read the writing.

6, water ball first coal gas cabinet under severe corrosion on the eastern side LG-5 dehydrator.

7, the transition across the west side of the day maintenance site liquefied gas point valve box pressurizer without thimble.


Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop on September 7, 2017, it is found that your unit has the following problems and needs to be rectified.

1. The fan room No. 3 fan is fixed to the front of the butterfly valve telescopic section of the pipeline, and is separated from the fixed suspension.

2, 3 #, 4 # fan discharge tube has no signage.

3, 1#, 2# fan chimney dehydrator valve screw without rubber holster.

4, 2# Converter east side oxygen point valve box door stack of debris and torch belt There is no fire extinguisher at the station.

    Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 7, 2017, it is found that your unit has the following problems and needs to be rectified.

1. The external network air supply 10# dehydrator water supply valve is not open.

2, the external network gas supply 11# water valve screw without rubber holster.

3. The south outer liquefied gas point valve box door of the east turn room is dropped.

4. The power line of the high pressure air liquefied gas pipe and the tire vibration motor in the east turn room is chaotic.

Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the continuous casting workshop on September 7, 2017, it is necessary to rectify the problem that your unit has the following problems.

1, 3# casting machine 5# baking bag at the joint of the torch and hose is damaged

Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 7, 2017, it is found that your unit has the following problems and needs to be rectified.

1, the first off-line in the package of the baking pan butterfly valve upper purge point using a single valve

2. There is no anti-static jumper wire for the new grille butterfly valve flange interface on the east side of the day shift cabin.

3, the external network 5# recycling dehydrator hydration small

4, the external network 5 # gas dehydrator dangerous source warning sign dirty, can not read the writing.

Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the No. 2 Workshop of the Continuous Casting on September 7, 2017, it was found that your unit had the following problems and needs to be rectified.

1. Place the chopsticks and other debris in the oxygen point valve box on the west side of the zero-meter two cold room of the billet casting machine.

2. There is no thimble in the pressurizer of the liquefied gas point valve box in the transitional west side daily maintenance site.

     Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Power 2 workshop on September 7, 2017, it is found that your unit has the following problems and needs to be rectified.

1. The first ball valve of the LG-5 dehydrator on the east side of the gas cabinet is seriously corroded .

Your unit must rectify the above issues as required by September 13, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Coding: YGJL6026

Time: 2017-9-8

The main site or to check the contents: the molten metal

80 tons:

1. There is slag on the wall of the 26# steel bag on the line, and the site is rectified.

2, online 28# steel water bag ring has open welding, has been processed

3, line 7 # iron water bag mouth is damaged

4, 4# machine big package rotating platform below the accident package has a drink bottle and other debris

5, 1# furnace under the ladle at the ladle is too full, on-site rectification

6, 1#125T crane West plate hook pin shaft pressure plate lacks a bolt, on-site rectification

120 tons:

1, 16# tank bottom leakage, tank wall cracking, site rectification

2, 5# slag can trunnion damage, disabled

3, 6# slag tank bottom leakage, disabled

4, 13# slag tank bottom leakage, tank wall cracking, disabled

5, 1# slag tank bottom leakage, disabled

6, 23# slag tank bottom leakage, disabled

7, 17# slag tank bottom leakage, disabled

8, 10# slag tank bottom leakage, disabled

9, 21# slag tank bottom leakage, disabled

10, 12# slag tank wall cracks, disabled

11, 18# slag cans scrapped

12, 1# small slag bottom crack

13, 2# small slag bucket trunnion side damage

14, 3# small slag bucket trunnion with slag steel

15,6# small slag bucket wall cracking, has been deactivated

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 8, 2017, it is found that your unit has the following problems and needs to be rectified.

1, online 7# hot metal bag mouth is damaged

Your unit must rectify the above issues as required by the 14th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the continuous casting workshop on September 8, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 4# machine big bag rotating platform below the accident package has a drink bottle and other debris

Your unit must rectify the above issues as required by September 14, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop 2 on September 8, 2017, it is found that your unit has the following problems and needs to be rectified.

1, 1# small slag bottom crack

2, 2# small slag bucket trunnion side damage

3, 3# small slag bucket trunnion with slag steel

Your unit must rectify the above issues as required by September 14, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Coding: YGJL6026

Time: 2017-9-15

checker:

Main part or content of inspection: comprehensive inspection

80T

1. The 40th steel ladle tracking card of the skateboard online is not signed by the person filling the form, and the site is rectified. Dong Shencong, Sun Shixiu

2. The grinding wheel on the grinder of the 1# skateboarding site is too worn and rectified on site. Sun Guangjun, Chang Jiansheng

3, 1# furnace pit 3# The south side of the skateboard sand filling platform on the south side of the furnace pit is covered with large steel slag, and the site is rectified. Liu Baoli, Liu Jianli

4, 1# The south end of the pit railway piled up too much steel slag, and the site was rectified. He Guosheng, Tian Smooth

5. A slag tank in the slag room is placed tilted, and the site is being rectified. Dong Liyong, Bian Liwei

6. Turn over the 6# big bag roasting bag bracket to place the skateboard to make the big bag bottom blowing oxygen pipe, clean up and rectify on site.耿塞晓,孙国永

7, the desulfurization of the east side 0 m ground sling large ring empty suspended in the special support plus, on-site standard rectification. Yan Zhande, Bi Xiuli

8. The slag car alarm on the north side of the 3# converter pit is not ringing, and the site is repaired and rectified. Liang Yihui, Li Yinxue

9. The compressed air hose on the north side of the slag house repairing steel sump is leaking, and the site is rectified.

10, No. 1 furnace power distribution room lacks a fire extinguisher

11. No. 1 No. 2 furnace steel huts each lack a fire extinguisher

12. The ground cover of the north side of the desulfurization station collapsed and the site was rectified.

13. Scrap pit hut without fire extinguisher

14. There is water in the door of the hydraulic station of No.1 machine, and the site is rectified.

15. The fire extinguisher on the east side of the second floor water distribution room of the first machine expired.

16. No. 2 refining furnace lacks a fire extinguisher

17. The liquefied gas valve box door on the south side of the slab repairing platform is not closed, and the site is rectified.

18. The electric control box door of the south wall of the billet turnaround room has not been closed, and the site has been rectified.

19, check the fan room staff Zhu Xuan, Yan Yuqi gas common sense qualified

20, spot check furnace Ma Wen, Chen Shuguang, Feng Xiuyong qualified for oxygen gun measures

21, spot check gas patrol worker Li Youchao, Liu Huanbo gas common sense qualified

22, spot check the gas inspection work Wang Shibin, Wang Jifeng gas common sense qualified

23, spot check oxygen workers, Yue Yuewen, Li Erqing safety regulations

24, check the liquefied gas station staff Li Xiaochen, Rong to the East air call qualified

120T

1. The steel bar on the east side of the 1# furnace steel rail has raised steel bars, and the site is rectified.

2, 12 # ladle bag with pin pin replaced with wire.

3. The steel wire rope hoe of the 拽 steel car under the converter furnace is about 1 meter long.

4, 2# slag truck south side track sweeper deformation, does not work.

5, 1 # casting machine one layer compressed air tank safety valve expired.

6, 1# refining furnace south wall has a scum of lifting.

7. There is no fire bucket in the fire sandbox at the hydraulic station door of the slab turning room.

8, 1#3# There is no fire extinguisher at the ladle roasting device.

9. The degassing station dedusting phase 1 No. 5 cylinder air source pipe runs, the site is rectified

10, the central pump station No. 4 circulating water pump transformer room door a bottle of fire extinguisher pressure is low, on-site rectification

11, the No. 1 furnace 8.8 meters distribution box inside the line exposed,

12, raw material 1#20T car northeast corner buffer is bad

13, the iron bag repairing the construction site guardrail open welding.

14. The unwelded wire is not used in the ladle repairing site welder.

15. There is debris in the fire sand below the 1# furnace oil station.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop on September 15, 2017, it was found that your unit had the following problems and needs to be rectified.

1. No fire extinguisher is available in the power distribution room of No.1 furnace

2, No. 1 No. 2 furnace steel huts each lack a fire extinguisher

3, scrap steel pit house without fire extinguisher

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the continuous casting workshop on September 15, 2017, it is found that your unit has the following problems and needs to be rectified.

1. The fire extinguisher on the east side of the second floor water distribution room of the first machine expires.

2. No. 2 refining furnace lacks a fire extinguisher

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop 2 on September 15, 2017, it was found that your unit had the following problems and needs to be rectified.

1. The steel wire rope head of the steel car under the converter furnace is about 1 meter long.

2, 2# slag slag car south side tracker deformation, does not work.

3, No.1 furnace 8.8 meters distribution box inside the line exposed,

4. There is debris in the fire sand below the 1# furnace oil station.

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Continuous Casting Workshop on September 15, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 1 # casting machine one layer compressed air tank safety valve expired.

2. The 1# refining furnace has a scum on the south wall.

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 15, 2017, it is found that your unit has the following problems and needs to be rectified.

1, 12 # ladle bag with pin pin replaced with wire.

2. There is no fire bucket in the fire sandbox at the door of the hydraulic station of the slab turning room.

3, 1#3# There is no fire extinguisher at the ladle roasting device.

4, the iron bag repairing the construction site guardrail open welding.

5, the ladle repair site welding machine does not use unsolved lines.

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Power 2 workshop on September 15, 2017, it was found that your unit had the following problems and needs to be rectified.

1. Raw material 1#20T trolley northeast corner buffer is bad

Your unit must rectify the above issues as required by September 22, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.  

Coding: YGJL6026

Time: 2017-9-18

Main part or content of inspection: safety guard

80T:

1, 1# converter furnace front control room block fire door motor protection cover off;

2. After the 1# converter furnace, the distribution box protection door is not closed, and the site is rectified;

3. The cover of the trench at the east gate of the first floor of the fan room is not covered, and the site is rectified;

4. The ground fence of the 3# and 2# belt joints of the bulk material is damaged;

5, 2#, 3# furnace furnace rear fire door motor on the protective cover fell;

6. The west side of the fan unit on the north side of the dehydrator is separated from the fixed door;

7, 1#-3# 3 sets of fan power lines after the furnace have no protective casing;

8, 3# refining furnace activities, a welding, a deformation;

9. The temporary pedal on the east side of the 1# machine shifting machine has no protective fence;

10, VSV repair package platform northeast corner guardrail lacking a corner;

11. The soft water pump station is broken by an acetylene bottle protective cap;

12. The second vehicle stall in the south of the bulk material warehouse is bad;

13. The protective door of the 7.6-meter platform hoisting hole of the converter is not installed;

The cable trough on the 14 and 130,000 dust removal platforms has no upper cover;

15. The protection of the east side of the bulk material warehouse is protected by a protective net;

120T:

1, 2# transfer station, one side of the south side of the protective bar open welding;

2. The deformation of the platform guardrail in the continuous casting of the billet in the billet;

3. The motor protection cover between the 1# slab equipment lacks a fixing bolt;

4, 2# furnace 1# high pressure pump motor coupling guard cover lacks a fixing bolt;

5, 2# furnace steel car duty room west side sewage pool cover is not covered;

6. The turbid ring hot water filter upper tower water pump protection cover lacks a fixing bolt;

7, 2# transfer station bucket belt guard cover hand hole door is not closed, lost material;

8. The second coupling guard cover of the south of the 1# furnace heat is not fixed;

9. There is no lower baffle under the guardrail of the roof ladder platform on the west side of the raw material cross-street platform;

10. In the square billet, the north side of the stairway is located on the north side of the stairway.

11. The electric hoist anti-decoupling device of the power center pump station is not standardized;

The observation hole on the vertical guard of the 12#2 transfer station is not closed;

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 18, 2017, it is found that your unit has the following problems and needs to be rectified.

1, VSV repair package platform northeast corner guardrail lacking a corner

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the smelting workshop on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 1# converter furnace front control room block fire door motor protection cover off;

2. The ground fence of the 3# and 2# belt joints of the bulk material is damaged;

3, 2#, 3# furnace behind the fire door motor on the protective cover fell;

4. The guard rail door on the west side of the north side of the fan unit is disconnected and fixed;

5, 1#-3# 3 sets of fan power lines after the furnace have no protective casing;

6. The second vehicle stall in the south of the bulk material warehouse is bad;

7. The protective door of the 7.6-meter platform hoisting hole of the converter is not installed;

8, the cable trough on the 130,000 dust removal platform has no cover;

9. The protection of the east side of the bulk material warehouse is protected by a protective net;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the continuous casting workshop on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 3# refining furnace activities, one open welding, one deformation;

2, 1# machine shifting machine east side temporary pedal without protective fence;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Power One Workshop on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1. The soft water pump station is broken by an acetylene bottle protective cap;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop 2 on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 2# transfer station, one side of the south side of the protective bar open welding;

2, 2# furnace 1# high pressure pump motor coupling guard cover lacks a fixing bolt;

3, 2# furnace steel car duty room west side sewage pool cover is not covered;

4, 2# transfer station bucket belt guard cover hand hole door is not closed, lost material;

5, 1# furnace heat between the second number of the second coupling guard is not fixed;

6. The observation hole on the vertical guard of the 2# transfer station is not closed;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Power 2 workshop on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1. The turbid ring hot water filter upper tower water pump protection cover lacks a fixing bolt;

2. There is no lower baffle under the guardrail of the roof ladder platform on the west side of the raw material across the sky.

3. The electric hoist anti-decoupling device of the power center pump station is not standardized;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Continuous Casting Workshop on September 18, 2017, it was found that your unit had the following problems and needs to be rectified.

1. The motor protection cover between the 1#1 slab equipment lacks a fixing bolt;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 18, 2017, it is found that your unit has the following problems and needs to be rectified.

1. In the billet, the north side of the stairway is located on the north side of the stairway.

2. The deformation of the platform guardrail in the continuous casting of the billet in the billet;

Your unit must rectify the above issues as required by the 24th of 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Coding: YGJL6026

Time: 2017-9-25

checker:

Main part or content of the inspection: pre-holiday inspection

80T

1. Fan room 4# fan, power cord, flexible line tube, damage, explosion, on-site rectification

2, the fan room 4# thin oil station is placed with a bucket of paint, on-site rectification

3, slag room repair steel slag car at the liquefied gas point valve box on the liquefied gas valve flange without anti-static bridging

4, 1# furnace after an argon valve leaking serious (small ball valve)

5, 3# furnace after the distribution box door grounding line off

6, the desulfurization station goes to the converter at the mouth of the oxygen valve, the lack of anti-static bridging

7, desulfurization station electric hoist anti-hook device is bad

8, 37# ladle wall slag

9. There is no protection at the secondary line terminal of the welding machine used in the welding of Tangshan Shengye West Material Yard.

10. Tangshan Shengye’s personnel took off their helmets while resting at the West Material Farm.

11, check 1# furnace one assistant Qiao Yu respirator qualified

12, check the position of the air breathing apparatus is normal

120 tons:

1. The failure of the front door stop of the furnace on the west side of the converter 1# furnace has been rectified

2, RH2# position lifting console door grounding wire loosened

3. Waste oil barrels at scrap site have been rectified

4, transition 3 #50 secondary hook limit is bad, on-site rectification

5. The fire extinguisher on the south side of the pig iron warehouse expired and the site was rectified.

6. The insulating rubber under the iron cantilever crane operation box is used for other purposes and has been rectified.

7. There is oil on the ground of the unpacking site, and the site is rectified.

8. There is a cigarette butt at the north gate of the power generation and distribution room.

9. The pumping station North Road manhole cover cover position, site rectification

Check the use of the power plant respirator; spot check should know the content of the situation; auxiliary: **, **; continuous casting: **, ** ; smelting: **, ** ; all qualified.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop on September 25, 2017, it was found that your unit had the following problems and needs to be rectified.

1. There is no anti-static crossover on the liquefied gas valve flange on the liquefied gas point valve box of the slag house repairing slag truck.

3. After 1# furnace, an argon valve leaks seriously (small ball valve)

3, 3# furnace after the distribution box door grounding line off

4, the desulfurization station goes to the converter, the oxygen valve at the mouth of the corridor is lack of anti-static bridging

5, desulfurization station electric hoist anti-hook device is broken

   Your unit must rectify the above issues as required by September 30, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 25, 2017, it is found that your unit has the following problems and needs to be rectified.

1, 37# ladle wall slag

     Your unit must rectify the above issues as required by September 30, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Coding: YGJL6026

Time: 2017-9-29

Main part or content of inspection: electricity safety

80 tons:

1, 1# baking package quick cutting valve flange anti-static jumper wire break

2, slag room 1--4# flameout detection is not used

3, 3# baking bag fast cutting can not be automatically cut off

4, 1# fan water seal packing leak

5, A11-3 channel is blocked by tons of bags

6, workshop 5-7 roasting device flameout detection is not used

7, auxiliary one off-line package roasting device flameout detection is not used

8, continuous casting a 5 # 中包 烤包Flange packing leak, the scene

9, VSV slab in the package of baking bag 3 # flange anti-static wire broken

120 tons:

1, recycling 4# gas dehydrator water valve packing drip

2, gas supply 8# gas dehydrator overflow port should be cleaned

3, LG-10 gas dehydrator switch water valve without ladder

4. The water leakage from the funnel below the overflow port of the gas supply 6# gas dehydrator causes water to accumulate on the ground.

5. There is no mark on the signboard at the sampling point of the heat meter on the east side of the gas cabinet.

6, LG-5 gas dehydrator, the second tank sewage valve has dripping phenomenon

7, gas cabinet 1#2# cabinet body release tube has dripping water phenomenon without leaking

8, 120T West valve platform gas dehydrator water valve packing drip

9,7# ladle roasting machine gas pipe pressure gauge against the wall, personnel operation can not observe pressure changes

10, 5# ladle roasting device discharge tube valve can not operate

11,3# ladle baking machine gas pipe pressure gauge no display

12, 1# slab offline baking packer fast cutting valve on the nitrogen pipe

13, 1# ladle baking bag gas pipe pressure gauge bad no pressure display

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the second casting workshop on September 29, 2017, it was found that your unit had the following problems and needs to be rectified.

1. 120T West valve platform gas dehydrator water valve packing root dripping;

Your unit must rectify the above issues as required by October 5, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

  Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 29, 2017, it is found that your unit has the following problems and needs to be rectified.

1, 1# baking pack quick cutting valve flange anti-static jumper wire break

2, slag room 1--4# flameout detection is not used

3, 3# baking bag fast cutting can not be automatically cut off

4, workshop 5-7 roasting device flameout detection is not used

5, auxiliary one offline bag roasting device flameout detection is not used

6, VSV slab in the package of baking bag 3 # flange anti-static wire broken

     Your unit must rectify the above issues as required by October 5, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Smelting Workshop on September 29, 2017, it was found that your unit had the following problems and needs to be rectified.

1, 1# fan water seal packing leaks

2. The A11-3 channel is blocked by tons of bags;

     Your unit must rectify the above issues as required by October 5, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the auxiliary workshop on September 29, 2017, it is found that your unit has the following problems and needs to be rectified.

1, recycling 4# gas dehydrator water valve packing drip

2, gas supply 8 # gas dehydrator overflow port should be cleaned

3, LG-10 gas dehydrator switch water valve without ladder

4. The water leakage from the funnel below the overflow port of the gas supply 6# gas dehydrator causes water to accumulate on the ground.

5, 7# ladle roasting machine gas pipe on the pressure gauge against the wall, personnel operations can not observe pressure changes

6, 5# ladle baking machine discharge tube valve can not operate

7,3# ladle baking machine gas pipe pressure gauge no display

8, 1# slab offline baking packer fast cutting valve on the nitrogen pipe

9, 1# ladle roasting machine gas pipe pressure gauge bad no pressure display

     Your unit must rectify the above issues as required by October 5, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Steelworks safety inspection and rectification notice

Coding: YGJL6027

In the safety inspection organized by the Power 2 workshop on September 29, 2017, it was found that your unit had the following problems and needs to be rectified.

1. There is no mark on the signboard at the sampling point of the heat meter on the east side of the gas cabinet.

2, LG-5 gas dehydrator, the second tank sewage valve has dripping phenomenon

3, gas cabinet 1#2# cabinet discharge tube has dripping water at the root of the tube

    Your unit must rectify the above issues as required by October 5, 2017. And report the rectification to the Safety Department of the Factory.

If there are special circumstances that cannot be rectified within the time limit, please submit the report in accordance with relevant regulations.

Metallic Frame Tent

A metallic Frame Tent has a sturdy and durable frame which is made of metal poles or tubing. Normally, the frame materials are stainless steel tubes or alloy and aluminum tubes, which can withstand wind and rain, even heavy snow, making it a reliable shelter in various weather conditions. The frame can provide the tent with structure and support, allowing it to stand upright without the need for guy ropes or stakes. This type of tent is typically larger in size and is often used for various fields such as field hospital, rescue purposes, fire fighting, military operations and disaster relief. Various sizes and colors are available for different fields of use. The metallic frame tent can provide a more comfortable and spacious shelter. The tent fabric is usually made from durable materials such as canvas, oxford, PVC fabrics or polyester, which are waterproof and UV-resistant and can withstand harsh weather conditions, ensuring that the interior remains dry and protected from the sun's harmful rays.

Metallic Frame Tent,Emergency Relief Tents,Disaster Relief Shelters,Army Medical Tents

Yangzhou Canway Outdoor Equipment Co.,Ltd , https://www.yzcanway.com